Another short week

The fixers have completed the ceiling and fire barrier installation in Totnes and are of to High Wycombe at the end of the week to install Prima demountable partitions.

Caterclad Hygienic wall linings have been completed and installation of Armstrong Orcal metal ceilings are underway at Haverhill Library. The operable wall head track & security shutter are programmed for installation next week.

The ceiling & drylining works have been completed for Needham Contracts in Haverhill.

Fire protection upgrade works start at the Department of Engineering on Monday.

Fire protection works for Millcam at Department of Chemistry are nearing completion and installation of ceilings due to commence shortly.

Installation of Avanti Designer partitioning has been completed for Hundred Housing.